Amid work to ready NASA's Ares I-X rocket for a long-awaited test flight next week, a presidential panel charged with reviewing the nation's manned space program submitted its completed report Thursday, concluding NASA's planned shuttle replacement will cost too much and take too long to build to be a viable option.
Even so, panel members said they looked forward to the $445 million test flight Tuesday and the data it will generate to help validate computer models and processes that will be useful in any future rocket design efforts.
"We do think it's appropriate to fly the Ares I-X," said Norman Augustine, former CEO of Lockheed Martin and chairman of the U.S. Human Spaceflight Plans Committee. "We think there are important things to be learned that will help the program."
Norman Augustine, left, chairman of a presidential review of manned space options, and panel member Edward Crawley, right, brief reporters Thursday.
(Credit: NASA)The panel's completed report contained no major surprises--an executive summary was released in late September that included the same five basic options for future manned space activity--but the coincidental timing of the report and next week's test flight highlighted the uncertain future of NASA's plans to replace the space shuttle and return to the moon.
"The premier conclusion of the committee is the human spaceflight program the United States is currently pursuing is one that's on an unsustainable trajectory," said Augustine. "We say that because of a mismatch between the scope of the program and the funds to support the program. That's of great concern to us because human spaceflight, where safety accounts for everything, is a very unforgiving sort of pursuit."
In the wake of the 2003 Columbia disaster, the Bush administration ordered NASA to finish the International Space Station and retire the shuttle by the end of 2010, and to develop new rockets and spacecraft to return astronauts to the moon by the early 2020s.
The plan NASA developed--the Constellation program--calls for a new rocket known as the Ares I, and an Apollo-like crew capsule called Orion, to ferry astronauts to and from low-Earth orbit. A large, unmanned heavy lift rocket known as the Ares V then would be built to launch Orion capsules and lunar landers to the moon.
President Obama expressed general support for the Constellation program during the presidential campaign, but earlier this year he ordered an independent review of NASA's manned space program in the context of the current budget environment. At the same time, the Office of Management and Budget cut some $3 billion from NASA's projected "out-years" budget, money earmarked for development of the Ares V.
Against that uncertain backdrop, NASA pressed ahead with development of the Orion capsule and the Ares I booster envisioned as a replacement for the space shuttle. The new rocket features an extended shuttle solid-fuel booster, a hydrogen-fueled upper stage and an escape rocket that could pull the crew capsule to safety in an emergency.
NASA plans to launch a test version of the rocket Tuesday on a sub-orbital flight to verify computer models being developed to help design the Ares I. For the test flight, a standard four-segment shuttle booster is being used, along with a dummy upper stage and an Orion capsule simulator that duplicate the mass and shape of the Ares I rocket.
"We've reviewed the Ares I and Orion elements of that program, which are the two parts that are principally underway," Augustine said Thursday. "We found those programs to be reasonably well managed, we found them to have technical problems of a nature that's probably not uncommon for complex undertakings of this type.
"It's our belief that given ample time and funds, the engineers at NASA and their contractors are certainly capable of solving those problems. So we think the program within itself has a very good likelihood of succeeding. The issue that comes up under Ares I is whether the program is useful when it has succeeded because of a mismatch of the time schedules and the costs with what will be needed for it to do."
While that observation suggests Augustine and the panel do not support continued development of Ares I, panel member Leroy Chiao, a former astronaut, said "it's important to emphasize that we were presenting options, not recommendations."
"Despite what's been going on in the blogosphere, the panel didn't come up saying (NASA) should cancel Ares I, which a lot of people think we actually did," he said in a telephone interview. "It's really up to the decision makers as to which path to go down. So Ares I is not dead by a long shot."
NASA believes the Ares I could be ready to fly by 2015. The Augustine panel concluded it would take until at least 2017 to complete the work, coming on line too late to provide more than token support to the International Space Station. In the meantime, NASA will be forced to buy seats on Russian Soyuz rockets, at $50 million per ticket, to get U.S. astronauts to and from the lab complex.
The Augustine report also concluded that NASA will be unable to extend human exploration beyond low-Earth orbit without additional funding, suggesting an additional $3 billion per year, plus a hedge against inflation, to fund a realistic space exploration program.
The panel did not make recommendations, but members seem to favor a commercially developed launch system to get astronauts to low-Earth orbit and a government-developed heavy lift rocket to extend human exploration to the moon and beyond.
The so-called "flexible path" option presented by the Augustine panel would allow NASA to launch orbital moon missions and even flights around Mars or to its moons by the early to mid 2020s, while long-term development of landers and associated hardware is developed in parallel.
"The current plan focuses on going to the moon (with) the longer term goal of going to Mars," Augustine said. "There are a lot of things one could do along the way that are very interesting, that let you build up gradually to the immense undertaking of the Mars program.
"The sort of thing we're thinking of, one could fly circumlunar missions, you could circumnavigate Mars, you could land on an asteroid, a near-Earth object, you could land on Phobos or Deimos, the martian moons, and do some very exciting science from there. It seems to us that is a more sensible program than to wait 15 years or so for the first major event."
A White House spokesman thanked the panel for its report, saying "the president has on numerous occasions confirmed his commitment to human space exploration, and the goal of ensuring that the nation is on a vigorous and sustainable path to achieving our boldest aspirations in space."
"Against a backdrop of serious challenges with the existing program, the Augustine committee has offered several key findings and a range of options for how the nation might improve its future human space flight activities," he said. "We will be reviewing the committee's analysis, and then ultimately the president will be making the final decisions."
JOHNSON SPACE CENTER, Houston--A presidential panel wrapping up a review of future U.S. manned space flight options delivered a grim assessment Wednesday, showing NASA's current plan to retire the shuttle, finish the space station and return to the moon by the early 2020s is not remotely feasible without a significant restoration of previously cut funding.
In the absence of a major spending increase, "our view is that it will be difficult with the current budget to do anything that's terribly inspiring in the human spaceflight area," said Norman Augustine, chairman of the Review of U.S. Human Space Flight Plans Committee.
Augustine's committee was set up by the Obama administration to examine NASA's current plans for retiring the shuttle, completing the space station, and returning to the moon as well as alternative strategies for moving beyond low-Earth orbit.
Anticipated funding versus currently planned budget - a $3 billion annual shortfall - threatens NASA's planned return to the moon by the early 2020s.
(Credit: NASA)The committee also is assessing how long NASA and its partners should operate the International Space Station. NASA currently has no money in its projected downstream budget to operate the $100 billion lab complex beyond 2015.
The Augustine committee believes the station cannot be operated without direct U.S. mission control and management and that it will cost some $1.5 billion to safely drive the huge complex out of orbit at the end of its life, whenever that might be.
NASA's current long-range plan, developed by the Bush administration in the wake of the 2003 Columbia disaster, is to complete the space station, retire the shuttle fleet, and develop a Apollo-like Orion crew capsule that will be launched to the station by new Ares 1 rockets.
During the gap between shuttle operations and the debut of Ares-1/Orion, U.S. astronauts will have to hitch rides to the station aboard Russian Soyuz rockets. NASA managers have assumed all along the station program would be extended and Ares 1/Orion would be used to deliver crews and supplies.
NASA also plans to develop a huge new unmanned heavy lift rocket called the Ares 5 that eventually will boost Orion capsules and Altair lunar landers to the moon for long-duration exploration. The Orion capsule, Ares rockets and lunar landers are the central pieces in NASA's Constellation program.
But during a final public hearing Wednesday in Washington, the Augustine panel provided a sobering look at NASA's projected budget and the requirements of various manned space flight scenarios.
Considering the Constellation program as the "program of record," panel member and former astronaut Sally Ride said NASA would need an additional $50 billion or so through 2020 to implement the program as currently planned. This scenario is known as the "unconstrained budget" case.
Former astronaut Sally Ride confers with manned space committee Chairman Norman Augustine before the start of a final public hearing Wednesday in Washington.
(Credit: NASA)It assumes the shuttle is retired on schedule and that the space station is deorbited in early 2016, an option no one on the panel seems to favor. In that scenario, the new Orion/Ares 1 system would have no destination until the Ares 5 heavy lifter debuted and moon flights began after 2021.
"In the unconstrained budget, Orion and Ares 1 arrive shortly after ISS is deorbited," Ride said. "And then you get human lunar return in 2021."
Assuming NASA is forced to live within the 2010 budget guidelines provided by the Obama administration, the Ares 5 heavy lift moon rocket would not be ready until the 2028 timeframe.
... Read moreThe Obama administration's fiscal 2010 NASA budget request includes $630 million in additional near-term funding for development of follow-on rockets and spacecraft needed for the agency's post-shuttle moon program, officials said Thursday. But most of the increase is from the administration's economic stimulus package, and projections through 2013 show a $3.1 billion reduction in overall funding for the program compared with 2009 projections.
Unveiling NASA's $18.7 billion 2010 budget on Thursday, acting Administrator Chris Scolese said the Obama administration had ordered an independent review of NASA's plans to replace the space shuttle with a combination of manned and unmanned Ares rockets, Apollo-style Orion capsules, and lunar landers needed to establish research stations on the moon by the early 2020s. The new rockets are the central elements of what NASA calls the Constellation program.
"You can expect a new administration coming in wants to understand where we're at, and is this the best way to go forward," Scolese said. "That's the purpose of the review, to understand that. Clearly if we're on the wrong path we should change. If you're asking me, 'Do I think we're on the wrong path,' no, I don't. We need to go off and demonstrate that. The review team needs to look at it and understand what we're doing and offer suggestions on how we could do it better."
A concept image showing NASA's Ares 1 rocket taking off.
(Credit: NASA)The review is expected to be completed by August. In the meantime, NASA will continue work on the Ares 1 rocket and Orion capsules the agency hopes to begin flying in March 2015. But contracts needed for initial development of the unmanned Ares 5 heavy lift booster needed for NASA's planned return to the moon are on hold pending the results of the review.
NASA's $18.7 billion budget request includes $1 billion in Recovery Act money and funds the addition of one shuttle flight to deliver an already-built physics experiment to the International Space Station.
Including next week's launch of the shuttle Atlantis on a fifth and final mission to service the Hubble Space Telescope, NASA plans nine more shuttle flights through September 30, 2010, the end of the fiscal year. If one or two flights slip beyond that target, NASA will need additional funding but the Obama administration has indicated it would support such a request if needed.
"What does this budget represent? I was surprised, in the last month I've seen the president three times," Scolese told reporters Thursday. "And I think that's an indication that NASA is something that this administration really cares about. The fact that we were highlighted in the budget discussions today with the (president's) science adviser is another indication of that. And I think you see it in this first bullet here, a $630 million increase to exploration, a $456 million increase to science and a $264 million increase to aeronautics. Those are significant increases."
Even so, the picture is much less rosy in the out years. Projections through 2013 in the fiscal 2010 budget package feature an asterisk after totals for the Exploration Systems Mission Directorate responsible for space station operations and development of the Constellation program.
The asterisks mean those numbers may change based on the results of the upcoming manned spaceflight review. But as of this writing, exploration faces $3.1 billion in cuts through 2013.
"We're up this year and next by about $630 million," agreed Douglas Cooke, associate administrator for the Exploration Systems Mission Directorate at NASA headquarters. "Over that time period, it's down about $3.1 (billion)."
Former NASA Administrator Mike Griffin said in a recent speech the projected funding shortfalls threaten America's leadership in manned space flight.
"In the last five years two presidents and two Congresses have provided the top-level direction necessary to ensure that the root cause of Columbia's loss--the lack of a guiding strategic vision for NASA--never happens again," Griffin said. "But apparently something more is needed. We're not matching the words with the necessary actions at the staff level. How soon we forget.
"Let me be clear. In a democracy, the proper purpose of the OMB (Office of Management and Budget) is not to find a way to create a Potemkin Village at NASA. It is not to create the appearance of having a real space program without having to pay for it. It is not to specify to NASA how much money shall be allocated for human lunar return by 2020. The proper purpose of the OMB is to work with NASA, as a partner in good government, to craft carefully vetted estimates of what is required to achieve national policy goals. The judgment as to whether the stated goals are too costly, or not, is one to be made by the nation's elected leadership, not career civil service staff."
Griffin said "no one can wrest leadership in space from the United States. We're that good. But we can certainly cede it, and that is the path we are on."
Sen. Bill Nelson, (D-Fla.), said he believes President Obama understands the value of space exploration and "I believe that's why the president has committed to finishing all nine space shuttle missions, regardless of how long it takes; and, to make full use of the International Space Station."
"This is a step in the right direction," he said. "But down the road the administration's budget does not match what candidate Obama said about the future of our space program. Still, he's assured me these numbers are subject to change, pending a review he has ordered of NASA."
A longer version of this story is available on the CBS News Space Place web site.