May 27, 2009 11:06 AM PDT

CERN's collider won't chill next winter

by Tom Espiner
  • Font size
  • Print
  • 4 comments

The Large Hadron Collider, currently undergoing repairs, will change its schedule and run through the winter to make sure the experiment provides workable results.

The European Centre for Nuclear Research (CERN) flagship particle accelerator has been out of action since September, when an electrical fault called a halt to an experiment to understand the fundamental physics of matter. It is scheduled to restart in September 2009.

Images: Where particles, physics theories collide

Click image for gallery on the Large Hadron Collider.

(Credit: Maximilien Brice for CERN)

On Wednesday, James Gillies, head of communications at CERN, said the LHC could carry on running over the subsequent months. Normally, CERN particle-acceleration operations cease in November for the winter, because energy costs throughout the winter months are prohibitively high.

"The schedule is fairly tight," Gillies told ZDNet UK. "Instead of shutting down for the winter, this year, we will start up in September, October, or later, and run continually until we have enough data in the can. We will run straight through the winter if necessary."

CERN is able to cover the energy cost of running the LHC during outside its schedule because it had had less expenditure while the experiment was halted, Gilles said. "We're getting the money from the standard CERN budget," he said. "If we hadn't had the incident last year, we would be running the LHC."

Gillies added that CERN would continue to be supplied by EDF on the French side and EOS on the Swiss side, and that EOS would provide energy through the cold season.

The energy demands of the LHC are high. The particle beams are designed to run at a maximum of 7 TeV, and have run at around 5 TeV. There is 350MJ stored in each beam, which CERN scientists estimate has enough energy to drill a 30m hole in copper.

The LHC experiment, designed to smash beams of nuclear particles into each other, was brought to a halt nine days after it was started. A fault in a copper bus-bar caused a resistive zone, which then prevented the normal operation of a quench. This caused an electrical arc, which punctured the cavity containing liquid helium used to supercool both the experiment and the magnets which direct and focus the particle beams.

The fault was the result of an insufficiently welded joint between two of the bus-bars, which are used to carry the superconducting cable. CERN beams department scientist Jorg Wenninger said in a presentation (PDF) on Monday that all the approximately 1,700 joints had been inspected. Many were found to have bad soldering or reduced electrical contact, the same problem that caused the initial incident.

A new quench-monitoring and protection system has been implemented that will give an early warning if any part of the superconducting coils or bus-bars develops high resistance, Gilles noted. He also said that more helium safety valves with a higher capacity were being installed.

Tom Espiner of ZDNet UK reported from London.

advertisement
 
Business supplies and services can get expensive. Get smart spending tips and learn about new cost-saving opportunities for your business
Recent posts from Cutting Edge
Shuttle Atlantis glides home after station visit
CERN particle accelerator sees first collisions
IBM taps into group language translation
Atlantis astronaut's wife gives birth 220 miles below
NASA signs 'The Rock' to make it seem cool
Large Hadron Collider up and running again
Fortified rice, fuel cells among Tech Award winners
Shuttle Atlantis completes smooth station linkup
Add a Comment (Log in or register) (4 Comments)
  • prev
  • 1
  • next
by fwjs28 May 27, 2009 1:46 PM PDT
YAAAY! i think the LHC is a bit overhyped, but it is very promising to the field of science with the so called God particle and many other tests...
Reply to this comment
by Seaspray0 May 27, 2009 9:04 PM PDT
The cause and effect in the article is mind numbing. It's akin to a splinter resulting in your finger being amputated. The only think I don't like about it is the long, long time it takes to put it back into operation. If they don't have all the kinks worked out, it'll set the schedule back several more months. I would like to see this thing fire off sometime while I'm still alive.
Reply to this comment
by mojojam May 28, 2009 11:38 AM PDT
I'm still waiting for the blackhole it created to devour the earth. :)
Reply to this comment
by Spanwite May 30, 2009 1:29 PM PDT
After they pushed the Start Button, for how long will it run this time.
Couple of weeks, before it's down for an other year again?
Maybe to much high tech to handle at this time!
Reply to this comment
(4 Comments)
  • prev
  • 1
  • next
advertisement

The browser battles go on and on

roundup From Firefox to IE and from Chrome to Opera and Safari, there's no sitting still for browser makers looking to keep their products fresh and competitive.

3G wireless still holds promise

The next generation of 4G wireless may get all the headlines, but advanced 3G technology will likely dominate services for the next few years.

About Cutting Edge

Keep up-to-date on cutting-edge research and what's new in a wide range of areas from robotics, space ventures and general science to automobile design and solar energy.

Add this feed to your online news reader

Cutting Edge topics

advertisement
Click Here
advertisement

Inside CNET News

Scroll Left Scroll Right